Categories
Previous Multi-Story Developments

The Peak

The Peak

2011 – Construction of an 11 level apartment block on the corner of Taranaki & Wigan St for Arrow International Using Comfloor 80 Steel Tray Flooring System Wallace worked with the Project Manager from Arrow on a construction methodology for this building to advance the programme.

After discussions on the merits of our and other formwork systems it was agreed our methodology of steel formwork shearwall system could achieve the required tight programme required. Piling of this site finished 1 week before Christmas and Wallace worked through the Christmas break to be ready for the first lift of structural steel by mid January. By the 7th of June the building reached Level 11 more than 2 months ahead of programme.